* I cleaned the vacuum chamber | * I cleaned the vacuum chamber | ||
{{: | {{: | ||
- | * I tested the M6 holes from vacuumchamber --> all threads are deep enough! | + | * I tested the all M6 holes from the vacuumchamber --> all threads are deep enough! |
{{: | {{: | ||
- | * 2x M4-breadboards (Incouple | + | * 2x M4-breadboards (incouple |
- | * I assembled the mounting with vitonballs and zerodur rods. --> We need two vitonballs of each metal sheet side. Otherwise the mounting is to wobbly! --> 8x new sinkings for the vitonballs! | + | * I assembled the mounting with vitonballs and zerodur rods. --> We need two vitonballs of each metal sheet side. Otherwise the mounting is to wobbly! --> 8x new sinkings for the vitonballs! If you fixed the mounting screws: tighten them crosswise! |
{{: | {{: | ||
+ | * Leaktest --> positiv :-/ --> New weld! | ||
+ | {{: | ||
+ | |||
+ | **ToDo in Hannover** | ||
+ | * Design and order new spacer instead ofeccentrical spacer (1mm from centre) | ||
+ | * 8x sinkings for the vitonballs | ||
+ | * 3x 1cm sinking grooves for the glasballs (1mm less then the theory). Use 90° milling head! Front: 2x vertical to the zerodur rods, Back: 1x parallel to the zerodur rods! Distance between the middle of the two mountings 28cm. | ||
+ | |||
+ | **ToDo in PTB** | ||
+ | * Sebastian took the vacuum chamber to the workshop for a new weld! |